Project 17DK0139
DPWH infrastructure contract
Contract ID:
17DK0139
Fingerprint:
b59106b9f10a40…aa0b51d36b Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Nov 22, 2017 (8 yrs 11 mo ago) · Target/actual end Apr 15, 2018
Description:
CONSTRUCTION OF TWO(2) UNITS ONE(1) STOREY WORKSHOP BUILDING(SCIENCE LABORATORY) @ SILANGANG MALICBOY NATIONAL HIGH SCHOOL, PAGBILAO, QUEZON
Category:
Buildings and Facilities
Implementing office:
DPWH Quezon 1st DEO · Region IV-A
Contractor:
E.A. AYALA CONSTRUCTION AND SUPPLY · DPWH contractor code 37139
Location:
Contract amount:
₱6,692,370.00 (₱6.7M)
Funding source:
Outside Infra - GAA 2017 DepEd BEFF
Budget year:
2017
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 584eb130e41c… | Nov 2, 2017 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - QUEZON 1ST ED | ₱6,349,720.54 |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.