Project 17DK0238
DPWH infrastructure contract
Contract ID:
17DK0238
Fingerprint:
9431e19e2b3ff6…11e9c06ba5 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 28, 2017 (8 yrs 10 mo ago) · Target/actual end Aug 24, 2018
Description:
CONSTRUCTION OF FOUR(4) STOREY-SCIENCE AND INFORMATION COMMUNICATION TECHNOLOGY LABORATORY BUILDING) @ BATANGAN NATIONAL HIGH SCHOOL, GENERAL NAKR, QUEZON
Category:
Buildings and Facilities
Implementing office:
DPWH Quezon 1st DEO · Region IV-A
Contractor:
Contract amount:
₱32,126,714.29 (₱32.1M)
Funding source:
Outside Infra - GAA 2017 DepEd BEFF
Budget year:
2017
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 38712d0f49d8… | Dec 27, 2017 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - QUEZON 1ST ED | ₱30,536,441.93 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25D00256 | Jun 9, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AGOS RIVER, PACKAGE Z, GENERAL NAKAR, QUEZON | On-Going | ₱93.6M |
| 25D00215 | Jun 3, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AGOS RIVER, INFANTA, QUEZON, PACKAGE R | On-Going | ₱187.2M |
| 25DK0037 | Jun 2, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY MAIGANG, GENERAL NAKAR, QUEZON | On-Going | ₱4.8M |
| 25D00014 | Apr 10, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AGOS RIVER, PACKAGE T, GENERAL NAKAR, QUEZON | On-Going | ₱94.0M |
| 25DK0051 | Apr 7, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY UMIRAY, GENERAL NAKAR, QUEZON | On-Going | ₱4.8M |
| 25D00008 | Mar 6, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AGOS RIVER, PACKAGE U, GENERAL NAKAR, QUEZON, PHASE 2 | On-Going | ₱188.2M |
| 25D00009 | Mar 6, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AGOS RIVER, PACKAGE V, GENERAL NAKAR, QUEZON | On-Going | ₱140.7M |
| 25D00010 | Mar 6, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AGOS RIVER, PACKAGE W, GENERAL NAKAR, QUEZON | On-Going | ₱140.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.