Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 17DM0031

DPWH infrastructure contract
Contract ID:
17DM0031
Fingerprint:
29bc0946c61653…c178112639 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 28, 2017 (9 yrs 8 mo ago) · Target/actual end Jun 27, 2017
Description:
CONSTRUCTION AND MAINTENANCE OF BRIDGES ALONG NATIONAL ROADS-REHABILITATION/MAJOR REPAIR OF PERMANENT BRIDGE, HINGUIWIN BRIDGE (B02950LZ), BARANGAY HINGUIWIN, PADRE BURGOS, QUEZON
Category:
Bridges
Implementing office:
DPWH Quezon 3rd DEO · Region IV-A
Contractor:
KKT CONSTRUCTION AND SUPPLY · DPWH contractor code 36852
Contract amount:
₱5,292,000.00 (₱5.3M)
Funding source:
Regular Infra - GAA 2017 MFO-1
Budget year:
2017

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
4f0f935d8562…Feb 21, 2017DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - QUEZON 3RD ED₱5,021,321.76

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25DM0175Jan 14, 2026CONSTRUCTION OF SUPER HEALTH CENTERS, PADRE BURGOS BAGONG PILIPINAS HEALTH CENTER, QUEZONOn-Going₱11.9M
25DM0065Mar 3, 2025NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - PADRE BURGOS BY- PASS ROAD, QUEZON, PADRE BURGOS, QUEZONOn-Going₱94.6M
25DM0052Feb 12, 2025BRIDGE PROGRAM - RETROFITTING/ STRENGTHENING OF PERMANENT BRIDGES - CABUYAO BR. (B02954LZ) ALONG P BURGOS-POTOTANIN JCT, PADRE BURGOS, QUEZONCompleted₱20.2M
24DM0110Apr 29, 2024CONSTRUCTION OF MULTIPURPOSE BUILDING, BARANGAY RIZAL, MUNICIPALITY OF PADRE BURGOS, QUEZON, PADRE BURGOS, QUEZONCompleted₱5.0M
24DM0092Apr 11, 2024CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BRGY. CABUYAO, PADRE BURGOS, QUEZONCompleted₱49.0M
24D00148Mar 18, 2024FY 2024 DPWH INFRASTRUCTURE PROGRAMORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMNETWORK DEVELOPMENT PROGRAMCONSTRUCTION OF BY-PASS AND DIVERSION ROADSPADRE BURGOS BY-PASS ROAD, QUEZON (PACKAGE 4)On-Going₱189.1M
24DM0004Feb 14, 2024ACCESS ROAD LEADING TO HINGUIWIN FALLS, BRGY. HINGUIWIN PADRE BURGOS, QUEZONCompleted₱19.3M
24DM0072Feb 14, 2024NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - PADRE BURGOS BY-PASS ROAD, PACKAGE 3Completed₱53.1M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.