Project 17DO0006
DPWH infrastructure contract
Contract ID:
17DO0006
Fingerprint:
c00925912812c9…3920dbc5b3 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 9, 2017 (9 yrs 9 mo ago) · Target/actual end May 22, 2017
Description:
MFO2-FLOOD MANAGEMENT SERVICES-CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG MANGO RIVER, MONTALBAN RIZAL
Category:
Flood Control and Drainage
Implementing office:
DPWH Rizal 2nd DEO · Region IV-A
Contractor:
THREE W BUILDERS, INC. · DPWH contractor code 10722
Location:
Contract amount:
₱28,811,136.78 (₱28.8M)
Funding source:
Regular Infra - GAA 2017 MFO-2
Budget year:
2017