Project 17E00017
DPWH infrastructure contract
Contract ID:
17E00017
Fingerprint:
f6bc8ce89563fd…67a9fd77b6 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 22, 2017 (9 yrs 5 mo ago) · Target/actual end Jan 26, 2020
Description:
IMPROVEMENT/WIDENING OF PUERTO PRINCESA NORTH ROAD K0194+561-K0196+558; K0208+540-K0209+915, TAYTAY, PALAWAN
Category:
GAA 2017 MFO-1
Implementing office:
DPWH MIMAROPA Region · MIMAROPA Region
Contractor:
THREE W BUILDERS, INC. · DPWH contractor code 10722
Location:
Not stated in the source
Contract amount:
₱95,363,273.53 (₱95.4M)
Funding source:
Regular Infra - GAA 2017 MFO-1
Budget year:
2017
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.