Project 17EA0040
DPWH infrastructure contract
Contract ID:
17EA0040
Fingerprint:
974473d2a33e5c…ed960dcc98 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 13, 2017 (9 yrs 8 mo ago) · Target/actual end Feb 21, 2018
Description:
CONSTRUCTION OF CABUYO FLOOD CONTROL
Category:
GAA 2017 MFO-2
Implementing office:
DPWH Marinduque DEO · MIMAROPA Region
Contractor:
M.G. SALAZAR CONSTRUCTION CORP. (FOR. M.G. SALAZAR · DPWH contractor code 4072
Location:
Contract amount:
₱10,168,678.87 (₱10.2M)
Funding source:
Regular Infra - GAA 2017 MFO-2
Budget year:
2017
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.