Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 17EB0143

DPWH infrastructure contract
Contract ID:
17EB0143
Fingerprint:
590070099991b1…9bda9e7f0e Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 5, 2018 (8 yrs 9 mo ago) · Target/actual end Dec 10, 2018
Description:
CLUSTER 2017BEFF-05: CONST. OF CLASSROOMS (BATCH 12): A) BALANSAY ES, 1STY5CL, B) FATIMA ES, 1STY3CL, C) KARYANDANGAN MIN. SCHOOL, 1STY2CL, MAMBURAO, OCC. MINDORO
Category:
GAA 2017 DepEd BEFF
Implementing office:
DPWH Mindoro Occidental DEO · MIMAROPA Region
Contractor:
M.A. GUINTO CONSTRUCTION (SAN JOSE BRANCH) · DPWH contractor code 26576
Location:
Not stated in the source
Contract amount:
₱9,987,041.83 (₱10.0M)
Funding source:
Outside Infra - GAA 2017 DepEd BEFF
Budget year:
2017

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.