Project 17ED0051
DPWH infrastructure contract
Contract ID:
17ED0051
Fingerprint:
845f6b6b88e687…0185d397e0 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 26, 2017 (9 yrs 7 mo ago) · Target/actual end Feb 28, 2018
Description:
OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE CALAPAN NORTH ROAD K0019+511-K0020+050, K0020+850-K0022+323, K0022+423-K0023+000, K0024+089-K0025+400, K0026+749-K0027+000, K0031+739-K0032+090, K0032+319-K0032+983, K0034+303-K0034+417, BACO-SAN TEODORO, OR
Category:
GAA 2017 MFO-1
Implementing office:
DPWH Mindoro Oriental DEO · MIMAROPA Region
Contractor:
STX ENTERPRISES · DPWH contractor code 21547
Contract amount:
₱42,557,912.51 (₱42.6M)
Funding source:
Regular Infra - GAA 2017 MFO-1
Budget year:
2017
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| f1e0d24fef44… | Mar 10, 2017 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - MINDORO ORIENTAL D | ₱42,557,912.51 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25ED0120 | May 26, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BRGY. STA. CRUZ, BACO, ORIENTAL MINDORO | On-Going | ₱142.7M |
| 25ED0132 | May 26, 2025 | INSTALLATION OF STREET LIGHTS ALONG CALAPAN NORTH ROAD K0007+000 - K0019+800, BACO - SAN TEODORO, ORIENTAL MINDORO | Completed | ₱96.5M |
| 25ED0133 | May 26, 2025 | REHABILITATION OF ROAD ALONG BARANGAY BURBULI, BACO, ORIENTAL MINDORO | Completed | ₱96.5M |
| 25ED0171 | May 21, 2025 | CONSTRUCTION OF MULTI - PURPOSE BUILDING, JULIO HERNANDEZ INTEGRATED SCHOOL, BARANGAY SANTA ROSA I, BACO, ORIENTAL MINDORO | Completed | ₱14.2M |
| 25E00238 | Apr 6, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE/ESPLANADE ALONG DULANGAN RIVER, BRGY. CANUBING II, STA. 000+000-STA. 000+305.50, CALAPAN, OR. MINDORO | On-Going | ₱236.9M |
| 25E00239 | Apr 6, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES- CONST. OF ROAD DIKE/ESPLANADE ALONG DULANGAN RIVER, BRGY. CANUBING II (DOWNSTREAM), STA. 000+320-STA. 000+613.90, CALAPAN, OR. MINDORO | On-Going | ₱237.0M |
| 25ED0146 | Mar 19, 2025 | REHABILITATION OF ROAD, BARANGAY POBLACION TO BARANGAY BANGKATAN, BACO, ORIENTAL MINDORO | Completed | ₱65.4M |
| 25ED0157 | Mar 19, 2025 | REHABILITATION OF ROAD, BARANGAY DULANGAN II TO BARANGAY DULANGAN III, BACO, ORIENTAL MINDORO | Completed | ₱143.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.