Project 17EF0038
DPWH infrastructure contract
Contract ID:
17EF0038
Fingerprint:
24694c8f731020…6f67263546 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 15, 2017 (9 yrs 7 mo ago) · Target/actual end Jan 30, 2018
Description:
CONSTRUCTION OF IRAAN FLOOD CONTROL
Category:
GAA 2017 MFO-2
Implementing office:
DPWH Palawan 2nd DEO · MIMAROPA Region
Contractor:
SYNDTITE CONSTRUCTION CORPORATION · DPWH contractor code 11597
As listed: SYNDTITE CONSTRUCTION CORPORATION (FORMERLY: R.C. TAGALA CONSTRUCTION)
Location:
Contract amount:
₱19,327,595.82 (₱19.3M)
Funding source:
Regular Infra - GAA 2017 MFO-2
Budget year:
2017
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| ffcbb86708a6… | Feb 24, 2017 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - PALAWAN 2ND DEO | ₱18,974,634.36 |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.