Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 17EH0050

DPWH infrastructure contract
Contract ID:
17EH0050
Fingerprint:
4e0866c0432ae6…cee39e2bbb Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 14, 2017 (9 yrs 4 mo ago) · Target/actual end Dec 15, 2018
Description:
CONSTRUCTION OF NEW PERMANENT BRIDGES MABINI NAP - LEON BRIDGE ALONG SIBUYAN CIRCUMFERENTIAL ROAD, SIBUYAN ISLAND, ROMBLON
Category:
GAA 2017 MFO-1
Implementing office:
DPWH Romblon DEO · MIMAROPA Region
Contractor:
ED1SON DEVELOPMENT & CONSTRUCTION INC. · DPWH contractor code 2400
Contract amount:
₱19,456,423.50 (₱19.5M)
Funding source:
Regular Infra - GAA 2017 MFO-1
Budget year:
2017

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.