Project 17FA0073

DPWH infrastructure contract
Contract ID:
17FA0073
Fingerprint:
48336e7fb47d83…eafc00e708 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 4, 2017 (8 yrs 11 mo ago) · Target/actual end Mar 20, 2018
Description:
CLUSTER 41-FLOOD CONTROL AND DRAINAGE PROTECTION WORKS DAMAGED BY TYPHOON 'NINA': REHAB/RESTORATION OF COMON LINE CANAL, TABACO CITY AND SAN ISIDRO PIPE CULVERT INTO BOX CULVERT, TABACO CITY
Category:
GAA 2017 NDRRMF
Implementing office:
DPWH Albay 1st DEO · Region V
Contractor:
Contract amount:
₱9,279,536.50 (₱9.3M)
Funding source:
Outside Infra - GAA 2017 NDRRMF
Budget year:
2017

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.