Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 17FC0357

DPWH infrastructure contract
Contract ID:
17FC0357
Fingerprint:
d8f19ace586400…ad4982e771 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jan 11, 2018 (8 yrs 10 mo ago) · Target/actual end May 19, 2019
Description:
CONST. OF TWO (2) STOREY FOUR (4) C/L (SCIENCE & ICT LAB.), SARAH JANE FERRER H/S, VINZONS CAMS. NOR
Category:
Buildings and Facilities
Implementing office:
Contractor:
A.C. RIVERO DEVELOPMENT CORPORATION · DPWH contractor code 5122
Contract amount:
₱15,735,254.47 (₱15.7M)
Funding source:
Outside Infra - GAA 2017 DepEd BEFF
Budget year:
2017

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
ac6c4fa3c98e…Dec 29, 2017DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAMARINES NORTE ED₱15,735,254.47

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.