Project 17FF0085

DPWH infrastructure contract
Contract ID:
17FF0085
Fingerprint:
94c51c341a069d…221a9da7b8 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 10, 2017 (9 yrs 2 mo ago) · Target/actual end Oct 10, 2018
Description:
NETWORK DEVELOPMENT-CONSTRUCTION OF MISSING GAPS CONNECTING NATIONAL ROADS, INCLUDING RIGHT OF WAY ALONG LALUD-GARCHITORENA ROAD, PINAMIHAGAN, LAGONOY, CAMARINES SUR STA. 0+000+ STA. 2+889.80
Category:
Roads
Implementing office:
Contractor:
PARTIDO CONSTRUCTION & SUPPLY · DPWH contractor code 20631
Contract amount:
₱79,741,722.95 (₱79.7M)
Funding source:
Regular Infra - GAA 2017 MFO-1
Budget year:
2017

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
384941a5cd5a…Aug 18, 2017DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAMARINES SUR 3RD₱79,741,722.95

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.