FY2026 GAA: ₱6.79T
PisoScan

Project 17FJ0163

DPWH infrastructure contract
Contract ID:
17FJ0163
Fingerprint:
d35851911aa8de…e690525994 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 5, 2019 (7 yrs 8 mo ago) · Target/actual end Sep 30, 2019
Description:
CONSTRUCTION OF BARANGAY HEALTH STATION, BRGY. TANQUE, PIO V. CORPUZ, MASBATE
Category:
Buildings and Facilities
Implementing office:
Contractor:
JOLAC'S CONSTRUCTION · DPWH contractor code 19901
Contract amount:
₱1,465,018.01 (₱1.5M)
Funding source:
Outside Infra - GAA 2017 DOH HFEP
Budget year:
2017

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
51e6e80a6727…Dec 27, 2018DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - MASBATE 2ND DEO₱1,465,018.01

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25FJ0046Jun 5, 2025CSSP- SIPAG- ACCESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES- CONSTRUCTION OF CONCRETE ROADS, BRGY. BADIANG, MUN. OF CATAINGAN TO BRGY. GUINDAWAHAN, MUNICIPALITY OF PIO V. CORPUS, MASBATECompleted₱9.6M
25FJ0049Jun 5, 2025CSSP- SIPAG- ACCESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES- CONSTRUCTION OF CONCRETE ROADS, BRGY. PALHO TO BRGY. BUENASUERTE, MUNICIPALITY OF PIO V. CORPUS, MASBATECompleted₱9.4M
25FJ0051Jun 5, 2025CSSP- SIPAG- ACCESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES- CONSTRUCTION OF CONCRETE ROADS, BRGY. TUBOG TO BRGY. GUINDAWAN, MUNICIPALITY OF PIO V. CORPUS, MASBATECompleted₱9.4M
24FJ0082Apr 4, 2025CSSP- SIPAG- ACCESS ROADS AND/ OR BRIDGES FROM NATIONAL ROADS/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES- CONSTRUCTION OF CONCRETE ROAD, BARANGAY PALHO- BARANGAY BUENASUERTE, PIO V. CORPUS, MASBATEOn-Going₱4.8M
24FJ0054May 27, 2024CSSP- SIPAG- ACCESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES- CONSTRUCTION OF CONCRETE ROAD, GUINDAWAHAN- CABANGRAYAN ROAD, PIO V. CORPUS, MASBATECompleted₱4.9M
24FJ0058May 17, 2024CONCRETING OF BRGY. BUNDOCAN TO BRGY. TUBIGAN FMR, BRGY. BUNDOCAN, PIO V. CORPUZ, MASBATECompleted₱14.9M
24FJ0064May 17, 2024CONVERGENCE AND SPECIAL SUPPORT PROGRAM- RAINWATER COLLECTORS SYSTEM (RWCS)Completed₱2.8M
24FJ0020Feb 15, 2024CSSP- BIP- ACESS ROADS AND/ OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES- CONSTRUCTION OF ROAD, GUINDAWAHAN- CABANGRAYAN ROAD, PIO V. CORPUZ, MASBATECompleted₱4.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.