Project 17GG0134
DPWH infrastructure contract
Contract ID:
17GG0134
Fingerprint:
0e6c1c59447652…e6cf23c8a8 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 14, 2017 (9 yrs 2 mo ago) · Target/actual end May 20, 2018
Description:
CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG JALAUR RIVER, BRGY. TABUCAN, BAROTAC NUEVO, ILOILO
Category:
Flood Control and Drainage
Implementing office:
DPWH Iloilo 2nd DEO · Region VI
Contractor:
SILVER DRAGON CONSTRUCTION & LUMBER & GLASS SUPPLY INC. · DPWH contractor code 30835
Location:
Contract amount:
₱48,999,725.98 (₱49.0M)
Funding source:
Regular Infra - GAA 2017 MFO-2
Budget year:
2017