Project 17GI0061
DPWH infrastructure contract
Contract ID:
17GI0061
Fingerprint:
c10adf46004428…7c64213d7e Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 15, 2017 (9 yrs 5 mo ago) · Target/actual end Aug 13, 2017
Description:
CONSTRUCTION/REHABILIATION OF WATER SUPPLY /SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS: CONSTRUCTION OF RAIN WATER COLLECTION SYSTEM - RWCS, ILOILO 2ND LEGISLATIVE DISTRICT
Category:
Water Provision and Storage
Implementing office:
DPWH Iloilo 4th DEO · Region VI
Contractor:
PESOM CONSTRUCTION SERVICES · DPWH contractor code 39923
As listed: PESOM CONSTRUCTION SERVICES (FORMERLY: PESOM BUILDERS AND CONSTRUCTION SUPPLY)
Contract amount:
₱3,270,995.69 (₱3.3M)
Funding source:
Regular Infra - GAA 2017 MFO-3
Budget year:
2017
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| b49a03db24f7… | May 30, 2017 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ILOILO 4TH DEO | ₱3,270,995.69 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GI0085 | Sep 9, 2025 | CONSTRUCTION OF SCHOOL BUILDING, SINAMAY ELEMENTARY SCHOOL, BARANGAY SINAMAY, ALIMODIAN, ILOILO | On-Going | ₱9.9M |
| 25GI0087 | Sep 9, 2025 | CONSTRUCTION OF SCHOOL BUILDING, ALIMODIAN NATIONAL COMPREHENSIVE HIGH SCHOOL, ALIMODIAN, ILOILO | On-Going | ₱24.6M |
| 25GI0053 | May 20, 2025 | CONSTRUCTION OF ROAD, BARANGAY QUINASPAN, ALIMODIAN, ILOILO | Completed | ₱9.8M |
| 25GI0060 | May 20, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LAYLAYAN, ALIMODIAN, ILOILO | On-Going | ₱4.9M |
| 25GI0061 | May 20, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BANCAL ELEMENTARY SCHOOL, ALIMODIAN, ILOILO | Completed | ₱4.9M |
| 25GI0063 | May 20, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, SITIO KANANGHAN, BARANGAY BUGA, LEON, ILOILO | Completed | ₱4.9M |
| 25GI0040 | Mar 25, 2025 | OFF-CARRIAGEWAY IMPROVEMENT: PAVING OF SHOULDERS - MANDURRIAO-SN MIGUEL- ALIMODIAN-MAASIN-CABATUAN RD - K0023 + 089 - K0023 + 860 | Completed | ₱34.6M |
| 25GI0064 | Mar 11, 2025 | CONSTRUCTION OF AGANAN FLOOD CONTROL STRUCTURE, JARO-AGANAN RIVER, BARANGAY POBLACION, ALIMODIAN, ILOILO | Completed | ₱45.1M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.