DPWH infrastructure contract
Contract ID:
17HA0010
Fingerprint:
401e398fb9292b…af2fa9720a Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 27, 2017 (9 yrs 6 mo ago) · Target/actual end Jun 5, 2017
Description:
MFO 1 NATIONAL ROAD NETWORK SERVICE ASSET PRESERVATION OF NATIONAL ROAD PREVENTIVE MAINTENANCE BASED
Category:
Roads
Implementing office:
DPWH Bohol 1st DEO · Region VII
Contractor:
AL CHRIS CONSTRUCTION · DPWH contractor code 12406
Contract amount:
₱3,065,727.50 (₱3.1M)
Funding source:
Regular Infra - GAA 2017 MFO-1
Budget year:
2017

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
d4f7a6676a54…Jan 30, 2017DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BOHOL 1ST ED₱3,065,727.50

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25HA0074Jun 2, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, DR. CECILIO PUTONG NATIONAL HIGH SCHOOL, TAGBILARAN CITY, BOHOLCompleted₱9.9M
25HA0084Jun 2, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING IN BARANGAY MANSASA, TAGBILARAN CITY, BOHOLCompleted₱4.8M
25HA0092Jun 2, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING IN BRGY. UBUJAN, TAGBILARAN CITY, BOHOLOn-Going₱4.9M
25HA0100Jun 2, 2025CONSTRUCTION OF ROAD AT MAGSAYSAY ST., BRGY. MANGA, TAGBILARAN, BOHOLCompleted₱8.9M
24HA0176May 30, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING AT DR. CECILIO PUTONG NATIONAL HIGH SCHOOL, TAGBILARAN CITY, BOHOLOn-Going₱2.4M
24HA0178May 30, 2025CONSTRUCTION OF DRAINAGE SYSTEM ALONG TAGBILARAN CITY EAST ES AND TAGBILARAN CITY CENTRAL ES, TAGBILARAN CITY, BOHOLCompleted₱4.8M
25HA0067May 30, 2025COMPLETION OF MULTI-PURPOSE BUILDING (COVERED COURT/EVACUATION CENTER) AT CAMP FRANCISCO DAGOHOY, TAGBILARAN CITY, BOHOLOn-Going₱4.9M
25HA0069May 30, 2025COMPLETION OF MULTI-PURPOSE BUILDINGS (DAMPAS E/S, 702ND COMMUNITY DEFENSE CENTER INCLUDING RELATED FACILITIES, CAMP BERNIDO, DAO, TAGBILARAN CITY, BOHOLOn-Going₱5.9M