Project 17HA0059
DPWH infrastructure contract
Contract ID:
17HA0059
Fingerprint:
1a720e77ef234c…fde1969b20 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 17, 2017 (9 yrs 3 mo ago) · Target/actual end Jan 8, 2018
Description:
CONSTRUCTION OF UBUJAN FLOOD CONTROL (BATERIA RIVER), TUBIGON, BOHOL PROJECT ID ; P00122191VS
Category:
Flood Control and Drainage
Implementing office:
DPWH Bohol 1st DEO · Region VII
Contractor:
Contract amount:
₱46,024,262.00 (₱46.0M)
Funding source:
Regular Infra - GAA 2017 MFO-2
Budget year:
2017
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25HA0062 | Jun 2, 2025 | COMPLETION OF MULTI-PURPOSE BUILDINGS, TUBIGON, BOHOL | Completed | ₱4.9M |
| 25HA0101 | Jun 2, 2025 | CONSTRUCTION OF ROAD, BRGY. CAWAYAN TO BRGY. BUNACAN TO BRGY. BOSONGON, TUBIGON, BOHOL | Completed | ₱19.8M |
| 24HA0175 | May 30, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY PANDAN, TUBIGON, BOHOL | Completed | ₱3.0M |
| 25HA0054 | May 30, 2025 | CONSTRTUCTION OF MULTI-PURPOSE BUILDING, TUBIGON WEST CENTRAL ELEMENTARY SCHOOL, TUBIGON, BOHOL | Completed | ₱4.9M |
| 25HA0008 | May 15, 2025 | PREVENTIVE MAINTENANCE - SECONDARY ROADS - THE CARLOS P. GARCIA CIRCUMFERENTIAL RD - K0026+096 - K0026+427, K0052+409 - K0052+941 | Completed | ₱29.6M |
| 25HA0049 | May 15, 2025 | WIDENING OF PERMANENT BRIDGES - MACA-AS BR. (B00018BH) ALONG THE PRESIDENT CARLOS P. GARCIA CIRCUMFERENTIAL RD | Completed | ₱39.2M |
| 25HA0098 | May 15, 2025 | REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS - JCT (TNR) CORTES-BALILIHAN-CATIGBIAN-MACAAS RD - K0048 + 400 - K0048 + 491 | On-Going | ₱96.4M |
| 25H00070 | Apr 16, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BARANGAY MATABAO, TUBIGON, BOHOL | On-Going | ₱9.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.