Project 17HB0058
DPWH infrastructure contract
Contract ID:
17HB0058
Fingerprint:
c07c2aa64ef13e…8e1dcbda68 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 6, 2017 (9 yrs 5 mo ago) · Target/actual end Aug 1, 2017
Description:
LOCAL INFRASTRUCTURE PROGRAM - ROADS AND BRIDGES - LOCAL ROADS - CONCRETING OF LOCAL ROAD BARANGAY DAGOHOY, BILAR, BOHOL, STA. 0+000 - STA. 0+170.00
Category:
Roads: Construction - PCCP, Roads: Construction - Slope Protection using Structural Measures (e.g. Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry)
Implementing office:
DPWH Bohol 3rd DEO · Region VII
Contractor:
J.F. ESTAPIA CONSTRUCTION · DPWH contractor code 40112
Location:
Contract amount:
₱1,880,015.00 (₱1.9M)
Funding source:
Regular Infra - Roads: Construction - PCCP, Roads: Construction - Slope Protection using Structural Measures (e.g. Revetment, Retaining Structures, Rock Netting, Concrete Crib, Shotcrete, MSE Walls, Gabions, Riprap, Masonry)
Budget year:
2017
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.