Project 17HC0042
DPWH infrastructure contract
Contract ID:
17HC0042
Fingerprint:
47b99c0cfed8f1…178b031489 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 10, 2017 (9 yrs 6 mo ago) · Target/actual end Aug 7, 2017
Description:
CLUSTER 8 - CY 2017 LOCAL INFRASTRUCTURE PROGRAM-REPAIR/REHAB. OF MULTI-PURPOSE BUILDINGS AT BRGY. KABANGKALAN (ISLAND), BRGY. SAGUISE (ISLAND ) AND BRGY. BAYOG (ISLAND), PRES.C.P. GARCIA, BOHOL
Category:
Buildings and Facilities
Implementing office:
DPWH Bohol 2nd DEO · Region VII
Contractor:
JECK CONSTRUCTION · DPWH contractor code 24189
Contract amount:
₱1,785,000.00 (₱1.8M)
Funding source:
Regular Infra - GAA 2017 LFP
Budget year:
2017
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 1f511c70b070… | Apr 27, 2017 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BOHOL 2ND DEO | ₱1,785,000.00 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25HC0093 | Jun 5, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, PRESIDENT CARLOS P. GARCIA, BOHOL | Completed | ₱4.8M |
| 24H00134 | Oct 18, 2024 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDING/FACILITIES, CONSTRUCTION OF STORM SURGE PROTECTION STRUCTURE AT BARANGAY PITOGO, CARLOS P. GARCIA, BOHOL | On-Going | ₱197.6M |
| 24HC0161 | Oct 15, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (MUNICIPAL HALL), CARLOS P. GARCIA, BOHOL (PHASE 2) | Completed | ₱9.9M |
| 24HC0146 | Oct 10, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (MUNICIPAL HALL), CARLOS P. GARCIA, BOHOL (PHASE 3) | Completed | ₱19.8M |
| 24HC0162 | Oct 10, 2024 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDINGS, PRES. CARLOS P. GARCIA, BOHOL | Completed | ₱9.9M |
| 24HC0129 | Oct 7, 2024 | REHABILITATION OF MULTI-PURPOSE BUILDINGS, CARLOS P. GARCIA, BOHOL | Completed | ₱19.5M |
| 24HC0111 | Sep 9, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (NEW MUNICIPAL HALL), CARLOS P. GARCIA, BOHOL (PHASE I) | Completed | ₱29.7M |
| 24HC0102 | Jul 15, 2024 | SUSTAINABLE INFRASTRUCTURE PROJECT ALLEVIATING GAPS (SIPAG)- FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES. CONSTRUCTION OF TUGAS SEAWALL, PRES. CARLOS P. GARCIA, BOHOL | On-Going | ₱144.7M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.