Project 17HF0118
DPWH infrastructure contract
Contract ID:
17HF0118
Fingerprint:
dfdc637b85ea17…36040dce3c Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 24, 2017 (9 yrs ago) · Target/actual end Nov 15, 2018
Description:
CONSTRUCTION OF ONE (1) UNIT - (1) STY - 3 CL, DPWH- DEPED STD. SCHOOL BUILDING (W/ ATTACHED CR), CABCABAN ELEMENTARY SCHOOL, BARILI, CEBU
Category:
Buildings and Facilities
Implementing office:
DPWH Cebu 3rd DEO · Region VII
Contractor:
PLD CONSTRUCTION AND DEVELOPMENT INC. (FORMERLY: PLD CONSTRUCTION) · DPWH contractor code 01859
Location:
Contract amount:
₱3,836,634.11 (₱3.8M)
Funding source:
Outside Infra - GAA 2017 DepEd BEFF
Budget year:
2017