Project 17J00009

DPWH infrastructure contract
Contract ID:
17J00009
Fingerprint:
849184e30f630b…0d7521bed0 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 5, 2017 (9 yrs 6 mo ago) · Target/actual end Apr 20, 2018
Description:
ROAD UPGRADING (UNPAVED TO PAVED) OF SIOCON-SIRAWAI-SIBUCO-LIMPAPA ROAD, ZAMBOANGA DEL NORTE, 2ND DEO, CHAINAGE 9380 - CHAINAGE 9995, L = 615.00 LNM., (K 2120 + 380.00-K 2120 + 995.00) (NET LENGTH: 615.00 LN.M.)
Category:
Roads
Implementing office:
DPWH Region IX · Region IX
Contractor:
M. ABUBAKAR CONST. AND ENGINEERING, INC. · DPWH contractor code 36365
Contract amount:
₱94,955,374.61 (₱95.0M)
Funding source:
Regular Infra - GAA 2017 MFO-1
Budget year:
2017

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25JJ0001Mar 27, 2025PREVENTIVE MAINTENANCE - SECONDARY ROADS, ZAMBOANGA WEST COASTAL RD (SIBUCO-LIMPAPA SECTION) - (S01152MN) CHAINAGE 5761 - CHAINAGE 9030On-Going₱55.3M
25JJ0003Mar 27, 2025REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, ZAMBOANGA WEST COASTAL RD (SIBUCO-LIMPAPA SECTION) - CHAINAGE 13301 - CHAINAGE 13521Completed₱5.0M
25JJ0005Mar 27, 2025REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, SIOCON-SIRAWAI-SIBUCO-LIMPAPA RD - K2120 + 179 - K2120 + 311, K2120 + 364 - K2120 + 409Completed₱53.9M
25JJ0006Mar 27, 2025REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, SIOCON-SIRAWAI-SIBUCO-LIMPAPA RD - K2112 + 440 - K2112 + 500, K2119 + 149 - K2119 + 192, K2120 + 075 - K2120 + 105Completed₱15.4M
25JJ0007Mar 27, 2025REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, SIOCON-SIRAWAI-SIBUCO-LIMPAPA RD - K2122 + 600 - K2122 + 635, K2123 + 140 - K2123 + 156Completed₱10.3M
25JJ0011Mar 27, 2025REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, SIOCON-SIRAWAI-SIBUCO-LIMPAPA RD - K2135 + 871 - K2135 + 907, K2136 + 316 - K2136 + 358On-Going₱34.7M
25JJ0012Mar 27, 2025REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, SIOCON-SIRAWAI-SIBUCO-LIMPAPA RD - K2140 + 301 - K2140 + 334, K2143 + 326 -K2143 + 352, K2143 + 478 - K2143 + 518Completed₱23.8M
25JJ0013Mar 27, 2025REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, SIOCON-SIRAWAI-SIBUCO-LIMPAPA RD - K2144 + 033 - K2144 + 091, K2144 + 728 - K2144 + 752, K2144 + 902 - K2144 + 942Completed₱34.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.