Project 17K00049

DPWH infrastructure contract
Contract ID:
17K00049
Fingerprint:
8b1b352b6836d5…db0b387f9b Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 13, 2017 (9 yrs 8 mo ago) · Target/actual end Feb 8, 2018
Description:
CONST./REHAB.OF REVETMENT ALONG ILIGAN RIVER(UPSTREAM OF TUBOD BR),INCL. ROW, TUBOD,LDN ILIGAN CITY
Category:
Flood Control and Drainage
Implementing office:
DPWH Region X · Region X
Location:
Not stated in the source
Contract amount:
₱91,500,000.02 (₱91.5M)
Funding source:
Regular Infra - GAA 2017 MFO-2
Budget year:
2017

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.