Project 17K00082
DPWH infrastructure contract
Contract ID:
17K00082
Fingerprint:
51e33933e32466…f276acfdc2 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 1, 2017 (9 yrs 8 mo ago) · Target/actual end Apr 19, 2018
Description:
WIDENING OF BRIDGES TO MORE THAN 2 LANES BOLO-BOLO BR ALONG BCIR,MIS.OR. 2ND LD
Category:
Bridges-Construction-Concrete, Roads: Construction - PCCP
Implementing office:
DPWH Region X · Region X
Contractor:
UKC BUILDERS, INC. · DPWH contractor code 10759
Contract amount:
₱91,243,818.64 (₱91.2M)
Funding source:
Regular Infra - Bridges-Construction-Concrete, Roads: Construction - PCCP
Budget year:
2017
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 82107bd05411… | Feb 1, 2017 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION X | ₱91,243,818.64 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26KL0143 | Sep 4, 2026 | NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - PRIMARY ROADS - BUTUAN CITY - CAGAYAN DE ORO CITY - ILIGAN CITY RD - K1454+653 - K1455+000, K1470+826 - K1471+080 | On-Going | ₱23.5M |
| 26KL0096 | Aug 10, 2026 | CONSTRUCTION/ UPGRADING/ REHABILITATION OF DRAINAGE ALONG NATIONAL ROAD - PRIMARY ROADS BUTUAN CITY - CAGAYAN DE ORO CITY - ILIGAN CITY RD - K1451+468 - K1452+100 | On-Going | ₱29.1M |
| 26KL0117 | Aug 10, 2026 | CONSTRUCTION OF PEDESTRIAN OVERPASS ALONG BCIR - K1450+600 BARANGAY MOLUGAN, EL SALVADOR CITY, MISAMIS ORIENTAL | On-Going | ₱19.6M |
| 25KL0135 | Feb 13, 2026 | CONSTRUCTION OF SUPER HEALTH CENTERS, HINIGDAAN BAGONG PILIPINAS HEALTH CENTERS, MISAMIS ORIENTAL | On-Going | ₱11.8M |
| 25KL0136 | Dec 11, 2025 | CONSTRUCTION OF SUPER HEALTH CENTERS, MOLUGAN BAGONG PILIPINAS HEALTH CENTERS, MISAMIS ORIENTAL | On-Going | ₱11.9M |
| 25K00407 | Jun 9, 2025 | CONSTRUCTION OF ROAD LEADING TO ABAGA AND SIKYOP FALLS, BARANGAY SAN FRANCISCO DE ASIS, EL SALVADOR, MISAMIS ORIENTAL | On-Going | ₱76.4M |
| 25K00414 | May 30, 2025 | CONST. OF DA-RFO 10 MAIN BUILDING PHASES I & II AND VARIOUS INFRASTRUCTURE PROJECTS, II GENERAL ADMINISTRATION AND SUPPORT SERVICES: INSTALLATION OF TELEPHONE LINES AND OTHER TELECOMMUNICATION FACILITIES, BRGY. POBLACION, EL SALVADOR CITY, MISAMIS ORIENTA | On-Going | ₱12.8M |
| 25KL0072 | May 27, 2025 | CONSTRUCTION OF ROAD, BARANGAY AMOROS, EL SALVADOR, MISAMIS ORIENTAL | On-Going | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.