Project 17K00154
DPWH infrastructure contract
Contract ID:
17K00154
Fingerprint:
c402500381791d…2bd6069cfc Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 23, 2017 (9 yrs 7 mo ago) · Target/actual end Aug 30, 2019
Description:
IMPRVT./WIDENING OF NATL RDS, OZAMIS-OROQUIETA RD,K1701+675-K1702+175,K1704+221-K1706+166,K1706+7668
Category:
Roads
Implementing office:
DPWH Region X · Region X
Contractor:
GRACE CONSTRUCTION CORPORATION · DPWH contractor code 3771
Contract amount:
₱134,883,796.28 (₱134.9M)
Funding source:
Regular Infra - GAA 2017 MFO-1
Budget year:
2017
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| a2b14d3d1270… | Feb 20, 2017 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION X | ₱134,883,796.28 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25KJ0117 | Oct 16, 2025 | ROAD WIDENING - PRIMARY ROADS OZAMIZ - PAGADIAN RD., K1669+287 - K1669+516.5, K1669+545.5 - K1670+070, K1691+324 - K1692+124.5, K1692+145.5 - K1692+566.982, K1692+678.941- K1692+789 | On-Going | ₱82.1M |
| 25KJ0039 | Jul 21, 2025 | CONSTRUCTION OF BY-PASS AND DIVERSION ROADS MOUNTAIN BYPASS ROAD, BRGY. MANAKA - GALA, OZAMIZ CITY, MISAMIS OCCIDENTAL | Completed | ₱29.1M |
| 25KJ0041 | Jul 21, 2025 | CONSTRUCTION OF BY-PASS AND DIVERSION ROADS MOUNTAIN BYPASS ROAD, (KINUMAN SUR - GALA SECTION), OZAMIZ CITY, MISAMIS OCCIDENTAL | Completed | ₱48.5M |
| 25KJ0042 | Jul 21, 2025 | CONSTRUCTION OF BY-PASS AND DIVERSION ROADS MOUNTAIN BYPASS ROAD, (KINUMAN NORTE - GALA SECTION), OZAMIZ CITY, MISAMIS OCCIDENTAL | Completed | ₱29.1M |
| 25KJ0043 | Jul 21, 2025 | CONSTRUCTION OF BY-PASS AND DIVERSION ROADS MOUNTAIN BYPASS ROAD, PUROK 5 - PUROK 6, BRGY. DIMALUNA SECTION, OZAMIZ CITY | Completed | ₱38.2M |
| 25KJ0044 | Jul 21, 2025 | CONSTRUCTION OF BY-PASS AND DIVERSION ROADS MOUNTAIN BYPASS ROAD,P3-P4 TABID SECTION, OZAMIZ CITY, MISAMIS OCCIDENTAL | Completed | ₱29.1M |
| 25KJ0045 | Jul 21, 2025 | CONSTRUCTION OF BY-PASS AND DIVERSION ROADS MOUNTAIN BYPASS ROAD, (P2-TABID SECTION, OZAMIZ CITY, MISAMIS OCCIDENTAL | Completed | ₱29.1M |
| 25KJ0093 | Jul 21, 2025 | RAINWATER COLLECTOR SYSTEM, MISAMIS OCCIDENTAL 2ND DEO | Completed | ₱2.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.