Project 17KC0030
DPWH infrastructure contract
Contract ID:
17KC0030
Fingerprint:
b8085ab8c26737…bca8905b1c Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 13, 2017 (9 yrs 5 mo ago) · Target/actual end Sep 22, 2017
Description:
CLUSTER 12 IMPROVEMENT OF MULTI-PURPOSE BUILDINGS, MANOLO FORTICH & SUMILAO, BUKIDNON 1) IMPVT. OF NBCC SCHOOL BDLG. TANKULAN, MANOLO FORTICH, BUKIDNON 2) IMPVT. OF MPB, SAN VICENTE, SUMILAO, BUKIDNON
Category:
Buildings and Facilities
Implementing office:
DPWH Bukidnon 3rd DEO · Region X
Contractor:
FOOTPRINTS CONSTRUCTION · DPWH contractor code 16713
Contract amount:
₱4,158,000.00 (₱4.2M)
Funding source:
Regular Infra - GAA 2017 LFP
Budget year:
2017
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 746cf76972fd… | Apr 26, 2017 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BUKIDNON 3RD DEO | ₱3,949,945.44 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26KC0057 | Sep 10, 2026 | PREVENTIVE MAINTENANCE ALONG SAYRE HIGHWAY - K1463 + 857 - K1464 + 824.87, MANOLO FORTICH, BUKIDNON | On-Going | ₱48.9M |
| 26KA0027 | May 29, 2026 | REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE ALONG SAYRE HIGHWAY K1486 + 000 - K1486 + 060, K1486 + 090 - K1486 + 130, K1486 + 500 - K1486 + 600 BARANGAY IMPALUTAO, IMPASUGONG, BUKIDNON 2ND LD | On-Going | ₱106.2M |
| 25KA0131 | Dec 16, 2025 | REPAIR/REHABILITATION OF CLASSROOMS, CAPITAN BAYONG ELEMENTARY SCHOOL, IMPASUG-ONG, BUKIDNON, BARANGAY CAPITAN BAYONG, IMPASUG-ONG, BUKIDNON | Completed | ₱9.8M |
| 25K00339 | May 26, 2025 | CONST. OF BY-PASS AND DIVERSION ROADS SAYRE HIGHWAY PARALLEL ROAD I (LIBONA - MANOLO FORTICH - IMPASUG-ONG SECTION), PACKAGE 26, BUKIDNON | On-Going | ₱174.9M |
| 25KA0044 | May 23, 2025 | CONSTRUCTION OF BOX CULVERT, BRGY. IMPALUTAO, IMPASUG-ONG, BUKIDNON BRGY. IMPALUTAO, IMPASUG-ONG, BUKIDNON 2ND LD | Completed | ₱9.8M |
| 25KA0058 | May 23, 2025 | CONCRETING OF ROAD LEADING TO COMMUNAL RANCH, IMPASUGONG, BUKIDNON, BARANGAY CAPITAN BAYONG, IMPASUG-ONG, BUKIDNON 2ND LD | On-Going | ₱49.0M |
| 25KA0063 | May 23, 2025 | CONSTRUCTION MULTI-PURPOSE BUILDING OF BRGY. IMPALUTAO, IMPASUGONG, BUKIDNON BARANGAY IMPALUTAO, IMPASUGONG, BUKIDNON | On-Going | ₱19.6M |
| 25KA0100 | May 23, 2025 | CONSTRUCTION OF ROAD LEADING TO COMMUNAL RANCH, BARANGAY CAPITAN BAYONG, IMPASUG-ONG, BUKIDNON BRGY. CAPITAN BAYONG, IMPASUG-ONG, BUKIDNON 2ND LD | On-Going | ₱96.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.