Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 17KH0004

DPWH infrastructure contract
Contract ID:
17KH0004
Fingerprint:
4b07cd08998743…59f8fa84da Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 16, 2017 (9 yrs 8 mo ago) · Target/actual end Jun 7, 2017
Description:
CONCRETING OF ROAD GOING TO TUBURAN NATIONAL HIGH SCHOOL, TUBURAN, CAGAYAN DE ORO CITY
Category:
Roads
Implementing office:
Contractor:
AT BUILDERS AND GENERAL MERCHANDISE · DPWH contractor code 38199
Contract amount:
₱2,970,000.00 (₱3.0M)
Funding source:
Regular Infra - GAA 2017 LFP
Budget year:
2017

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
1b2e836fce76…Jan 25, 2017DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAGAYAN DE ORO CIT₱2,814,464.37

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25KL0124May 28, 2025CONSTRUCTION OF CARABAO VALLEY ROAD, BARANGAY AWANG, OPOL, MISAMIS ORIENTALOn-Going₱48.5M
25K00362May 26, 2025CONSTRUCTION OF BY-PASS AND DIVERSION ROADS OPOL DIVERSION ROAD (OPOL-CANITO-AN), PACKAGE 18, MISAMIS ORIENTALOn-Going₱47.8M
25KL0129May 26, 2025CONSTRUCTION OF BRIDGE, SITIO PIGTAO, BARANGAY NANGCAON, OPOL, MISAMIS ORIENTALOn-Going₱96.0M
25KL0110May 23, 2025CONCRETING OF ZONE 4-MALAORO ROAD, BARANGAY MALANANG, OPOL, MISAMIS ORIENTALOn-Going₱49.0M
25KL0113May 23, 2025CONCRETING OF BINIGWAYAN-MALAORO ROAD, BARANGAY MALANANG, OPOL, MISAMIS ORIENTALOn-Going₱48.6M
25KL0117May 23, 2025CONSTRUCTION OF DRAINAGE, BARANGAY POBLACION AND BARANGAY TABOC, OPOL, MISAMIS ORIENTALOn-Going₱48.6M
25KL0006Mar 19, 2025CONSTRUCTION OF WATER SUPPLY SYSTEM, BARANGAY BONBON, OPOL MISAMIS ORIENTALOn-Going₱4.9M
25KL0017Mar 19, 2025CONSTRUCTION OF PEDESTRIAN OVERPASS ALONG BCIR-K1448+420, BRGY. LUYONG BONBON, OPOL, MISAMIS ORIENTALOn-Going₱19.6M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.