Project 17KJ0179
DPWH infrastructure contract
Contract ID:
17KJ0179
Fingerprint:
ee40896ade108d…ffd6897371 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jan 12, 2018 (8 yrs 10 mo ago) · Target/actual end Mar 17, 2019
Description:
CONSTRUCTION OF CLASSROOMS TABID NATIONAL HIGH SCHOOL, OZAMIZ CITY, MISAMIS OCCIDENTAL
Category:
Buildings and Facilities
Implementing office:
DPWH Misamis Occidental 2nd DEO · Region X
Contractor:
GENETIAN BUILDERS AND ENTERPRISES INCORPORATED (FORMERLY: GENETIAN BUILDERS) · DPWH contractor code 18052
Contract amount:
₱11,561,858.92 (₱11.6M)
Funding source:
Outside Infra - GAA 2017 DepEd BEFF
Budget year:
2017
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.