Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 17LA0349

DPWH infrastructure contract
Contract ID:
17LA0349
Fingerprint:
de4f7a71b7d651…103c4e7321 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jan 5, 2018 (8 yrs 10 mo ago) · Target/actual end Jun 23, 2018
Description:
CONSTRUCTION OF ONE (1) UNIT, TWO (2) STOREY, SIX (6) CLASSROOM BUILDING @ KAPOC ES, MABINI (DOÑA ALICIA), COMPOSTELA VALLEY PROVINCE
Category:
Buildings and Facilities
Implementing office:
Contractor:
EXACT CONSTRUCTION · DPWH contractor code 15975
Contract amount:
₱13,815,617.11 (₱13.8M)
Funding source:
Outside Infra - GAA 2017 DepEd BEFF
Budget year:
2017

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
3997be0fb785…Dec 15, 2017DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - COMPOSTELA VALLEY₱13,815,617.11

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25LA0076Aug 8, 2025CONSTRUCTION OF (COMPLETION) MULTI-PURPOSE BUILDING, BARANGAY ANITAPAN NATIONAL HIGH SCHOOL, MABINI, DAVAO DE OROOn-Going₱3.0M
25LA0083Jul 24, 2025CONSTRUCTION OF MULTI PURPOSE BUILDING, BARANGAY GOLDEN VALLEY, MABINI, DAVAO DE OROOn-Going₱4.7M
25LA0090Jul 24, 2025CONSTRUCTION OF ROAD, MANANGCOL, GOLDEN VALLEY - ANITAPAN, MABINI, DAVAO DE OROOn-Going₱34.3M
25LA0070May 23, 2025CONSTRUCTION OF REVETMENT ALONG TUNGA CREEK, MABINI, DAVAO DE OROOn-Going₱96.5M
24LA0142Mar 10, 2025ROAD CONCRETING FROM CADUNAN NATIONAL HIGHWAY TO NEW MABINI SANITARY LANDFILL SITE MABINI, DAVAO DE ORO, PHASE 2On-Going₱9.4M
24LA0143Mar 10, 2025ROAD CONCRETING SITIO VACA TO NEW SLAUGHTERHOUSE TO PANGIBIRAN, MABINI, DAVAO DE ORO, PHASE 2On-Going₱13.8M
24L00336Jan 20, 2025REHABILITATION/RECONSTRUCTION OF REVETMENT FLOOD MITIGATION STRUCTURE ALONG TAGBALAOBAO RIVER LOCATED AT PUROKS MADRE DE CACAO, MABOLO, NARRA, AND MAHOGANY, BRGY. PINDASAN, MABINI, DAVAO DE OROOn-Going₱42.9M
24L00338Jan 20, 2025REHABILITATION/RECONSTRUCTION OF REVETMENT FLOOD MITIGATION STRUCTURE ALONG TAGBALAOBAO RIVER LOCATED AT PUROK PARK B-2 AND RIVERSIDE, BRGY. PINDASAN, MABINI, DAVAO DE OROCompleted₱42.2M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.