Project 17M00032
DPWH infrastructure contract
Contract ID:
17M00032
Fingerprint:
6276748823b14d…34bfffd90c Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 19, 2017 (9 yrs 7 mo ago) · Target/actual end Dec 31, 2017
Description:
ROAD WIDENING OF MARBEL MAKAR ROAD, K1670+278-K1671+500 (CHAINAGE 9863-CHAINAGE 11104), K1671+597-K1671+673 (CHAINAGE 11201-CHAINAGE 11277), K1672+673-K1675+125 (CHAINAGE 12278-CHAINAGE 14683), POLOMOLOC, SOUTH COTABATO
Category:
Roads
Implementing office:
DPWH Region XII · Region XII
Contractor:
CHL CONSTRUCTION & DEVELOPMENT ENTERPRISES, INC. (15001) / THREE W BUILDERS, INC. · DPWH contractor code 10722
Contract amount:
₱143,253,198.13 (₱143.3M)
Funding source:
Regular Infra - GAA 2017 MFO-1
Budget year:
2017
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25MB0145 | May 11, 2026 | CONSTRUCTION OF SCHOOL HEALTH FACILITIES, POBLACION POLOMOLOK NATIONAL HIGH SCHOOL, POLOMOLOK, SOUTH COTABATO | On-Going | ₱2.9M |
| 25MB0123 | Nov 10, 2025 | CONCRETING OF SITIO PALACASAM TO SITIO ALNAMANG, BRGY. PALKAN FMR, BRGY. PALKAN, POLOMOLOK, SOUTH COTABATO | Completed | ₱12.2M |
| 25MB0111 | Oct 6, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING AT UPPER KLINAN ELEMENTARY SCHOOL, BARANGAY UPPER KLINAN, POLOMOLOK, SOUTH COTABATO | On-Going | ₱4.9M |
| 25MB0109 | Sep 22, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BARANGAY CANNERY SITE, POLOMOLOK, SOUTH COTABATO | Completed | ₱4.8M |
| 25MB0133 | Aug 4, 2025 | CONSTRUCTION OF SCHOOL BUILDING, LAMCALIAF INTEGRATED SCHOOL, BRGY. LAMCALIAF, POLOMOLOK, SOUTH COTABATO | Completed | ₱5.0M |
| 25MB0135 | Aug 4, 2025 | CONSTRUCTION OF SCHOOL BUILDING, PALKAN ELEMENTARY SCHOOL, BRGY. PALKAN, POLOMOLOK, SOUTH COTABATO | Completed | ₱4.9M |
| 24M00221 | Jul 23, 2025 | CONSTRUCTION OF BRIDGE ALONG MARBEL-MAKAR ROAD, K1670 + 075, POLOMOLOK, SOUTH COTABATO | Completed | ₱28.7M |
| 25MB0044 | Jul 18, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), POLOMOLOK CREEK INTEGRATED SCHOOL, BARANGAY MAGSAYSAY, POLOMOLOK, SOUTH COTABATO | Completed | ₱4.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.