FY2026 GAA: ₱6.79T
PisoScan

Project 17MC0187

DPWH infrastructure contract
Contract ID:
17MC0187
Fingerprint:
8fc64155f10145…7a4133ad7d Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 25, 2017 (8 yrs 10 mo ago) · Target/actual end Mar 19, 2018
Description:
CONSTRUCTION OF 1 UNIT 1 STOREY 2 CL SCHOOL BUILDING WITH ATTACHED TOILET AT MARCIANO DAHAN HS, ARAKAN, NORTH COTABATO
Category:
Buildings and Facilities
Implementing office:
DPWH Cotabato 2nd DEO · Region XII
Contractor:
JARGON CONSTRUCTION & SUPPLY · DPWH contractor code 23474
Contract amount:
₱2,963,925.10 (₱3.0M)
Funding source:
Outside Infra - GAA 2017 DepEd BEFF
Budget year:
2017

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
945fd8bf9cf8…Dec 14, 2017DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NORTH COTABATO 1ST₱2,963,925.10

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25MC0100Jun 24, 2025CONSTRUCTION OF RAIN WATER COLLECTOR SYSTEM (RWCS) (CLUSTER-1), ALL IN NORTH COTABATOCompleted₱2.6M
24M00068May 15, 2025CONSTRUCTION OF CONCRETE BRIDGE -DOROLUMAN-PRESIDENT ROXAS-KADINGILAN ROAD, COTABATO (NORTH COTABATO) PHASE II, STA 0+990 - STA 1+098, ARAKAN, NORTH COTABATOOn-Going₱26.0M
25MC0043Apr 17, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG TINANAN RIVER , PACKAGE 1, BARANGAY MALIBATUAN, ARAKAN, COTABATOOn-Going₱93.6M
25MC0044Apr 17, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG TINANAN RIVER, PACKAGE 2, BARANGAY MALIBATUAN, ARAKAN, COTABATOCompleted₱112.2M
25MC0045Apr 17, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG TINANAN RIVER, PACKAGE 3, BARANGAY MALIBATUAN, ARAKAN, COTABATOOn-Going₱112.3M
25MC0046Apr 2, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG TINANAN RIVER, PACKAGE 4, BARANGAY MALIBATUAN, ARAKAN, COTABATOCompleted₱31.5M
25MC0063Mar 9, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY MALIBATUAN, ARAKAN, NORTH COTABATOCompleted₱2.0M
24M00079Nov 11, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING, COTABATO FOUNDATION COLLEGE OF SCIENCE AND TECHNOLOGY, BARANGAY DOROLUMAN, ARAKAN, NORTH COTABATOCompleted₱14.8M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.