Project 17OB0427
DPWH infrastructure contract
Contract ID:
17OB0427
Fingerprint:
35ef2153740b52…44953d51a6 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 27, 2017 (8 yrs 10 mo ago) · Target/actual end Feb 24, 2018
Description:
CONSTRUCTION/COMPLETION OF RANCHO 1 MULTI-PURPOSE BUILDING, BRGY. CONCEPCION DOS, MARIKINA CITY
Category:
Buildings and Facilities
Implementing office:
DPWH Metro Manila 1st DEO · National Capital Region
Contractor:
ACC CARASCO ENTERPRISE INC. · DPWH contractor code 38180
Contract amount:
₱2,398,462.28 (₱2.4M)
Funding source:
Regular Infra - GAA 2017 LFP
Budget year:
2017
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DN0104 | Jun 16, 2025 | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - CORAZON C. AQUINO AVE. - K0029+580 - K0030+197 ANTIPOLO CITY (SECOND DISTRICT) | On-Going | ₱18.7M |
| 25DN0105 | Jun 16, 2025 | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - MARIKINA - INFANTA RD - K0035+908.00 - K0036+000.00 ANTIPOLO CITY (SECOND DISTRICT) | Completed | ₱4.8M |
| 25DN0113 | Jun 16, 2025 | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - MARIKINA - INFANTA RD - K0035+000.00 - K0035+738.00 ANTIPOLO CITY (SECOND DISTRICT) | Completed | ₱30.9M |
| 25DO0077 | Jun 5, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD BARANGAY SILANGAN TO BARANGAY | On-Going | ₱47.2M |
| 25DN0096 | May 29, 2025 | ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS - CORAZON C. AQUINO AVE. - K0029+400 - K0029+500, ANTIPOLO CITY (SECOND DISTRICT) | Completed | ₱5.1M |
| 25DN0100 | May 29, 2025 | IMPROVEMENT OF ROAD, OLALIA ROAD, PHASE II, BARANGAY STA CRUZ AND BARANGAY DELA PAZ, ANTIPOLO CITY (FIRST DISTRICT) | On-Going | ₱9.6M |
| 25DN0102 | May 29, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE, PUROK 5, ZONE 8, BARANGAY CUPANG, ANTIPOLO CITY, RIZAL (SECOND DISTRICT) | On-Going | ₱5.0M |
| 25DN0103 | May 29, 2025 | CONSTRUCTION OF SLOPE PROTECTION, BO. CUPANG/ LITTLE TONDO, BARANGAY CUPANG, ANTIPOLO CITY, RIZAL (SECOND DISTRICT) | On-Going | ₱5.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.