Project 17OD0101
DPWH infrastructure contract
Contract ID:
17OD0101
Fingerprint:
885dd4f88ddbcb…bcfad68d22 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 26, 2017 (9 yrs 3 mo ago) · Target/actual end Jun 24, 2018
Description:
CONSTRUCTION / REHABILITATION OF SAPANG ALAT, PHASE II STATION 0+820 TO STATION 1+720, CALOOCAN CITY
Category:
Flood Control and Drainage
Implementing office:
DPWH Metro Manila 3rd DEO · National Capital Region
Contractor:
A.D. GONZALES JR. CONSTRUCTION AND TRADING CO., INC. · DPWH contractor code 10012
As listed: A.D. GONZALES JR. CONSTRUCTION & TRADING CO. INC.
Contract amount:
₱84,591,919.90 (₱84.6M)
Funding source:
Regular Infra - GAA 2017 MFO-2
Budget year:
2017
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 9e9907242a9d… | Jul 3, 2017 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - METRO MANILA 3RD E | ₱84,591,919.90 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25OD0370 | Jul 28, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, NORTH OLYMPUS, BARANGAY 172, CALOOCAN CITY | On-Going | ₱9.2M |
| 25OD0371 | Jul 28, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 156, CALOOCAN CITY | On-Going | ₱10.5M |
| 25OD0373 | Jul 28, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), CELINA HOMES, BARANGAY 168, CALOOCAN CITY | On-Going | ₱4.8M |
| 25OD0374 | Jul 28, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), PHASE 2, BARANGAY 171, CALOOCAN CITY | Completed | ₱4.8M |
| 25OD0375 | Jul 28, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (SPORTS COMPLEX), BARANGAY 176, CALOOCAN CITY (PHASE 3) | On-Going | ₱23.9M |
| 25OD0376 | Jul 28, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. 180, CALOOCAN CITY | On-Going | ₱28.6M |
| 25OD0368 | Jul 21, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY 153, CALOOCAN CITY | On-Going | ₱28.7M |
| 25OD0360 | Jul 9, 2025 | CONSTRUCTION (COMPLETION) PUP NORTH CALOOCAN CITY CAMPUS ACADEMIC BUILDING INCLUDING GROUND IMPROVEMENT (PHASE 6), BRGY. 168, CALOOCAN CITY | On-Going | ₱139.3M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.