Project 17PK0011

DPWH infrastructure contract
Contract ID:
17PK0011
Fingerprint:
42a3b3ebaf3b04…0e6929964e Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 20, 2017 (9 yrs 4 mo ago) · Target/actual end Oct 25, 2017
Description:
CONSTRUCTION OF MAATOP FLOOD CONTROL ALONG SALTAN RIVER
Category:
Flood Control and Drainage
Implementing office:
DPWH Upper Kalinga DEO · Cordillera Administrative Region
Contractor:
BHM CONSTRUCTION · DPWH contractor code 30724
Location:
Not stated in the source
Contract amount:
₱9,643,518.13 (₱9.6M)
Funding source:
Regular Infra - GAA 2017 MFO-2
Budget year:
2017

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
0960a605113a…Feb 10, 2017DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - UPPER KALINGA DEO₱9,358,836.81

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.