Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 17PK0046

DPWH infrastructure contract
Contract ID:
17PK0046
Fingerprint:
780ed2adf9c96b…cefc887d20 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 3, 2017 (9 yrs 4 mo ago) · Target/actual end Jun 14, 2019
Description:
CONSTRUCTION OF WATER SYSTEM (LEVEL II) PASIL, KALINGA
Category:
Water Provision and Storage
Implementing office:
DPWH Upper Kalinga DEO · Cordillera Administrative Region
Contractor:
SONBLESSED CONSTRUCTION AND SUPPLY · DPWH contractor code 40230
Location:
Not stated in the source
Contract amount:
₱4,602,162.33 (₱4.6M)
Funding source:
Regular Infra - GAA 2017 LFP
Budget year:
2017

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
7668ae62a085…Jun 15, 2017DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - UPPER KALINGA DEO₱4,602,162.33

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.