Project 17PK0081
DPWH infrastructure contract
Contract ID:
17PK0081
Fingerprint:
879591262f34c4…5a5f857cc4 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 30, 2017 (9 yrs ago) · Target/actual end Mar 28, 2019
Description:
RECONSTRUCTION OF SLOPE PROTECTION ALONG KALINGA-ABRA ROAD (BALBALASANG SECTION II)
Category:
Flood Control and Drainage
Implementing office:
DPWH Upper Kalinga DEO · Cordillera Administrative Region
Contractor:
BHM CONSTRUCTION · DPWH contractor code 30724
Location:
Not stated in the source
Contract amount:
₱38,185,277.20 (₱38.2M)
Funding source:
Outside Infra - GAA 2017 NDRRMF
Budget year:
2017
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 5bcb39cb18ef… | Oct 18, 2017 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - UPPER KALINGA DEO | ₱38,185,277.20 |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.