Project 17RD0115
DPWH infrastructure contract
Contract ID:
17RD0115
Fingerprint:
e7941c924e54a0…037ee9f1cc Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Nov 15, 2017 (9 yrs ago) · Target/actual end Mar 12, 2018
Description:
CONSTRUCTION OF ONE (1) UNIT ONE (1) STOREY THREE (3) CLASSROOMS AT GENARO P. ALVAREZ ELEMENTARY SCH
Category:
Buildings and Facilities
Implementing office:
DPWH Negros Occidental 3rd DEO · Negros Island Region
Contractor:
H.L.J. CONSTRUCTION & ENTERPRISES · DPWH contractor code 18080
As listed: H.L.J CONSTRUCTION & ENTERPRISES
Contract amount:
₱4,235,011.92 (₱4.2M)
Funding source:
Outside Infra - GAA 2017 DepEd BEFF
Budget year:
2017
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26RC0016 | Aug 3, 2026 | WIDENING OF PERMANENT BRIDGES - CARTAGENA BR. 1 (B00241NR) ALONG BACOLOD SOUTH RD (KABANKALAN-HINOBA-AN SECTION) | On-Going | ₱19.8M |
| 26RC0009 | Jun 15, 2026 | REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS - BACOLOD SOUTH RD (KABANKALAN-HINOBA-AN SECTION)-K0163+510 - K0164+140 | On-Going | ₱13.6M |
| 25RC0017 | Apr 27, 2026 | CONSTRUCTION OF 2STY 8CL SCHOOL BUILDING, GENARO P. ALVAREZ ELEMENTARY SCHOOL, SIPALAY CITY, NEGROS OCCIDENTAL | On-Going | ₱27.5M |
| 25RC0018 | Apr 27, 2026 | CONSTRUCTION OF 2STY 8CL SCHOOL BUILDING, SIPALAY CITY NATIONAL HIGH SCHOOL, SIPALAY CITY, NEGROS OCCIDENTAL | On-Going | ₱27.4M |
| 25RC0019 | Apr 7, 2026 | REPAIR/REHABILITATION OF CLASSROOM, BARANGAY V ES, CITY OF SIPALAY, NEGROS OCCIDENTAL | Completed | ₱5.9M |
| 25RC0007 | Nov 13, 2025 | CONSTRUCTION OF EVACUATION CENTER - CONSTRUCTION (COMPLETION) OF EVACUATION CENTER IN SIPALAY, NEGROS OCCIDENTAL | Completed | ₱9.9M |
| 25GM0004 | Mar 25, 2025 | RECONSTRUCTION TO CONCRETE PAVEMENT - BACOLOD SOUTH RD (KABANKALAN-HINOBAAN SECTION) - K0177+900 - K0179+730, K0182+645 - K0182+903, SIPALAY CITY AND HINOBAAN, NEGROS OCCIDENTAL | Completed | ₱53.1M |
| 25GM0015 | Feb 24, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG SIPALAY RIVER, SIPALAY CITY, NEGROS OCCIDENTAL | Completed | ₱96.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.