Project 18AH0004

DPWH infrastructure contract
Contract ID:
18AH0004
Fingerprint:
7e6a2c37296d4c…87167dceb4 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 20, 2018 (8 yrs 8 mo ago) · Target/actual end Apr 20, 2018
Description:
CONCRETING OF BRGY. ROAD, BRGY. DALANGUIRING, URBIZTONDO, PANGASINAN
Category:
Roads
Implementing office:
Contractor:
JF CRUZ TRADING & CONSTRUCTION CORPORATION · DPWH contractor code 36856
Contract amount:
₱1,880,994.14 (₱1.9M)
Funding source:
Regular Infra - GAA 2018 LP
Budget year:
2018

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25AJ0101Aug 6, 2025CONSTRUCTION SLOPE PROTECTION, BRGY. PAYAR, SAN CARLOS CITY, PANGASINANOn-Going₱4.8M
25AJ0120Aug 6, 2025ACCESS ROAD LEADING TO MINOR BASILICA OF SAINT DOMINIC DE GUZMAN, SAN CARLOS CITY, PANGASINANOn-Going₱47.2M
25A00545Jul 4, 2025BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF MULTI - PURPOSE BUILDING, BRGY. TURAC, CITY OF SAN CARLOS, PANGASINANCompleted₱4.8M
25AJ0100Jun 5, 2025CONSTRUCTION OF FLOOD CONTROL (WATER IMPOUNDING), BRGY. RIZAL, SAN CARLOS CITY, PANGASINANOn-Going₱4.8M
25AJ0102Jun 5, 2025CONSTRUCTION OF DRAINAGE CANAL, BRGY. MATAGDEM, SAN CARLOS CITY, PANGASINANOn-Going₱4.8M
25AJ0107Jun 5, 2025CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG SAN JUAN RIVER, BARANGAY MESTIZO NORTE, SAN CARLOS CITY, PANGASINANOn-Going₱19.1M
25AJ0124Jun 5, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PANAMINDITAAN CREEK, BARANGAY TALANG, SAN CARLOS CITY, PANGASINANOn-Going₱47.2M
25AJ0125Jun 5, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SAN JUAN RIVER, BOLOSAN SECTION, SAN CARLOS CITY, PANGASINANOn-Going₱47.2M