FY2026 GAA: ₱6.79T
PisoScan

Project 18AJ0057

DPWH infrastructure contract
Contract ID:
18AJ0057
Fingerprint:
0095b6a238a781…1260e5d1de Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 20, 2018 (8 yrs 8 mo ago) · Target/actual end Apr 5, 2018
Description:
REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. MALIWARA, SAN CARLOS CITY, PANGASINAN
Category:
Buildings and Facilities
Implementing office:
Contractor:
LEZA CONSTRUCTION AND SUPPLY · DPWH contractor code 25565
As listed: LEZA CONSTRUCTION & SUPPLY
Contract amount:
₱495,001.88 (₱495.0K)
Funding source:
Regular Infra - GAA 2018 LP
Budget year:
2018

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
2cc43b8a9abb…Feb 6, 2018DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - PANGASINAN IV DEO₱495,196.68

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25AJ0101Aug 6, 2025CONSTRUCTION SLOPE PROTECTION, BRGY. PAYAR, SAN CARLOS CITY, PANGASINANOn-Going₱4.8M
25AJ0120Aug 6, 2025ACCESS ROAD LEADING TO MINOR BASILICA OF SAINT DOMINIC DE GUZMAN, SAN CARLOS CITY, PANGASINANOn-Going₱47.2M
25A00545Jul 4, 2025BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF MULTI - PURPOSE BUILDING, BRGY. TURAC, CITY OF SAN CARLOS, PANGASINANCompleted₱4.8M
25AJ0100Jun 5, 2025CONSTRUCTION OF FLOOD CONTROL (WATER IMPOUNDING), BRGY. RIZAL, SAN CARLOS CITY, PANGASINANOn-Going₱4.8M
25AJ0102Jun 5, 2025CONSTRUCTION OF DRAINAGE CANAL, BRGY. MATAGDEM, SAN CARLOS CITY, PANGASINANOn-Going₱4.8M
25AJ0107Jun 5, 2025CONSTRUCTION OF SLOPE PROTECTION STRUCTURE ALONG SAN JUAN RIVER, BARANGAY MESTIZO NORTE, SAN CARLOS CITY, PANGASINANOn-Going₱19.1M
25AJ0124Jun 5, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PANAMINDITAAN CREEK, BARANGAY TALANG, SAN CARLOS CITY, PANGASINANOn-Going₱47.2M
25AJ0125Jun 5, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SAN JUAN RIVER, BOLOSAN SECTION, SAN CARLOS CITY, PANGASINANOn-Going₱47.2M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.