Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 18BH0118

DPWH infrastructure contract
Contract ID:
18BH0118
Fingerprint:
d014e1fcf79027…b3f754f6bf Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 26, 2018 (8 yrs 3 mo ago) · Target/actual end Apr 30, 2019
Description:
CONSTRUCTION OF TWO-STOREY (4 CLASSROOMS) 2 SCIENCE LABORATORY BUILDING
Category:
Buildings and Facilities
Implementing office:
Contractor:
JMD-68 BUILDERS · DPWH contractor code 36943
Contract amount:
₱9,356,281.76 (₱9.4M)
Funding source:
Outside Infra - GAA 2018 DepEd BEFF
Budget year:
2018

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
1dd07c3d29e6…Jul 11, 2018DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ISABELA 4TH DEO₱9,356,281.76

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25BH0120Aug 18, 2025BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY DIBULO, DINAPIGUE, ISABELAOn-Going₱4.9M
25BH0235Aug 18, 2025BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BUCAL SUR, DINAPIGUE, ISABELAOn-Going₱4.8M
25BH0300Aug 11, 2025BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDING/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY AYOD, DINAPIGUE, ISABELAOn-Going₱2.9M
25BH0147Aug 6, 2025BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BUCAL NORTE, DINAPIGUE, ISABELAOn-Going₱4.8M
24BH0296Oct 7, 2024SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF DIMALUADE FLOOD CONTROL STRUCTURE, SECTION 1, DINAPIGUE, ISABELACompleted₱96.3M
24BH0297Oct 4, 2024SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF BUCAL NORTE FLOOD CONTROL STRUCTURE, SECTION 3, DINAPIGUE, ISABELAOn-Going₱96.3M
24BH0298Sep 24, 2024SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF BUCAL NORTE FLOOD CONTROL STRUCTURE, SECTION 4, DINAPIGUE, ISABELACompleted₱96.5M
24BH0299Sep 24, 2024SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF DEDEKKEL FLOOD CONTROL STRUCTURE, SECTION 1, DINAPIGUE ISABELACompleted₱96.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.