Project 18CD0022
DPWH infrastructure contract
Contract ID:
18CD0022
Fingerprint:
7c9b435e3ddc7e…59d99a6d8a Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Mar 1, 2018 (8 yrs 8 mo ago) · Target/actual end Aug 25, 2018
Description:
CONSTRUCTION/REHABILITATION OF ROAD, BRGY. MAHARLIKA, CITY OF SAN JOSE DEL MONTE, BULACAN
Category:
Flood Control: Construction - Drainage (e.g., Closed and Open Conduits, Spillway), Roads: Rehabilitation - PCCP
Implementing office:
DPWH Bulacan 2nd DEO · Region III
Contractor:
M.S. RAMOS CONSTRUCTION INC. (FORMERLY: M.S. RAMOS · DPWH contractor code 31684
Contract amount:
₱27,898,921.40 (₱27.9M)
Funding source:
Regular Infra - Flood Control: Construction - Drainage (e.g., Closed and Open Conduits, Spillway), Roads: Rehabilitation - PCCP
Budget year:
2018
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CD0222 | Jul 15, 2025 | REPLACEMENT OF PERMANENT WEAK BRIDGES KAY TIALO BR. (B00136LZ) ALONG NCR/BULACAN BDRY-BIGTE-IPO DAM RD (PHASE III) | Terminated | ₱0 |
| 25OD0367 | Jul 9, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE 10, PACKAGE 3 LOT 71, BARANGAY 176, CALOOCAN CITY | On-Going | ₱9.7M |
| 25CD0192 | May 26, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE 1, CITY OF SAN JOSE DEL MONTE, BULACAN | On-Going | ₱96.0M |
| 25CD0193 | May 26, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, (OPERATIONS CENTER - DISTRICT 1), BARANGAY KAYPIAN, CITY OF SAN JOSE DEL MONTE, BULACAN (PHASE III) | On-Going | ₱48.0M |
| 25CD0206 | May 26, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (ALS BUILDING), TUNGKONG MANGGA ELEMENTARY SCHOOL BARANGAY TUNGKONG MANGGA, CITY OF SAN JOSE DEL MONTE, BULACAN | Completed | ₱19.2M |
| 25CD0154 | Apr 15, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY MAHARLIKA, SAN JOSE DEL MONTE, BULACAN | Completed | ₱2.9M |
| 25CD0155 | Apr 15, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY STA. CRUZ 3, SAN JOSE DEL MONTE, BULACAN | Completed | ₱4.8M |
| 25CD0157 | Apr 15, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY MINUYAN PROPER, SAN JOSE DEL MONTE, BULACAN | Completed | ₱4.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.