Project 18CD0027

DPWH infrastructure contract
Contract ID:
18CD0027
Fingerprint:
98383c5e557648…dd1aa7b8c7 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 24, 2018 (8 yrs 3 mo ago) · Target/actual end Nov 7, 2018
Description:
CONSTRUCTION SLOPE PROTECTION, SAN MARTIN DE PORRES, SAN JOSE DEL MONTE CITY, BULACAN
Category:
Flood Control and Drainage
Implementing office:
DPWH Bulacan 2nd DEO · Region III
Contractor:
WBX CONSTRUCTION, INC. · DPWH contractor code 28370
As listed: WBX CONSTRUCTION, INC (FORMERLY WBX CONSTRUCTION)
Contract amount:
₱940,330.13 (₱940.3K)
Funding source:
Regular Infra - GAA 2018 LP
Budget year:
2018

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
f46770c9d1a8…Jul 13, 2018DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BULACAN 2ND DEO₱940,330.13

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CD0222Jul 15, 2025REPLACEMENT OF PERMANENT WEAK BRIDGES KAY TIALO BR. (B00136LZ) ALONG NCR/BULACAN BDRY-BIGTE-IPO DAM RD (PHASE III)Terminated₱0
25OD0367Jul 9, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE 10, PACKAGE 3 LOT 71, BARANGAY 176, CALOOCAN CITYOn-Going₱9.7M
25CD0192May 26, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE 1, CITY OF SAN JOSE DEL MONTE, BULACANOn-Going₱96.0M
25CD0193May 26, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, (OPERATIONS CENTER - DISTRICT 1), BARANGAY KAYPIAN, CITY OF SAN JOSE DEL MONTE, BULACAN (PHASE III)On-Going₱48.0M
25CD0206May 26, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (ALS BUILDING), TUNGKONG MANGGA ELEMENTARY SCHOOL BARANGAY TUNGKONG MANGGA, CITY OF SAN JOSE DEL MONTE, BULACANCompleted₱19.2M
25CD0154Apr 15, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY MAHARLIKA, SAN JOSE DEL MONTE, BULACANCompleted₱2.9M
25CD0155Apr 15, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY STA. CRUZ 3, SAN JOSE DEL MONTE, BULACANCompleted₱4.8M
25CD0157Apr 15, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY MINUYAN PROPER, SAN JOSE DEL MONTE, BULACANCompleted₱4.8M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.