Project 18CE0024
DPWH infrastructure contract
Contract ID:
18CE0024
Fingerprint:
1bfeca4167ccf9…a40b789df6 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 21, 2018 (8 yrs 5 mo ago) · Target/actual end Jun 1, 2018
Description:
NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS, JCT PINAGPANAAN - RIZAL - PANTABANGAN RD. K0134+375 - K135+000, K0135+000 - K0135+305
Category:
Roads
Implementing office:
DPWH Nueva Ecija 1st DEO · Region III
Contractor:
ADROIT EJD CONSTRUCTION CORP. (FORMERLY: ADROIT CONSTRUCTION) · DPWH contractor code 11169
Contract amount:
₱8,453,381.18 (₱8.5M)
Funding source:
Regular Infra - GAA 2018 OO-1
Budget year:
2018
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CE0195 | Jun 30, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY GEN. RICARTE, LLANERA, NUEVA ECIJA | Completed | ₱5.9M |
| 25CE0196 | Jun 30, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY VICTORIA, LLANERA, NUEVA ECIJA | Completed | ₱4.9M |
| 25CE0256 | Mar 25, 2025 | ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - TERTIARY ROADS, JCT PINAGPANAAN-RIZAL-PANTABANGAN RD - K0136 + 000 - K0137 + 000 | Completed | ₱14.7M |
| 25CE0109 | Mar 20, 2025 | REHABILITATION OF ROAD, BARANGAY SANTA BARBARA TO BARANGAY VILLA VINIEGAS, LLANERA, NUEVA ECIJA | Completed | ₱9.7M |
| 25CE0140 | Feb 17, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BAGUMBAYAN, LLANERA, NUEVA ECIJA | Completed | ₱3.9M |
| 25CE0102 | Feb 14, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY VICTORIA, LLANERA, NUEVA ECIJA | Completed | ₱4.7M |
| 25CE0112 | Feb 14, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY PLARIDEL, LLANERA, NUEVA ECIJA | Completed | ₱4.0M |
| 25CE0113 | Feb 11, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY SAN FRANCISCO, LLANERA, NUEVA ECIJA | Completed | ₱2.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.