Project 18CF0053
DPWH infrastructure contract
Contract ID:
18CF0053
Fingerprint:
bcd7abd49acd83…305b0773d5 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Apr 10, 2018 (8 yrs 7 mo ago) · Target/actual end Aug 31, 2018
Description:
CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF SLOPE PROTECTION ALONG DIGMALA RIVER CONTROL, ARIENDO SECTION, BONGABON, NUEVA ECIJA
Category:
Flood Control and Drainage
Implementing office:
DPWH Nueva Ecija 2nd DEO · Region III
Contractor:
D.S. PAMINTUAN CONSTRUCTION · DPWH contractor code 31868
Contract amount:
₱48,885,768.86 (₱48.9M)
Funding source:
Regular Infra - GAA 2018 OO-2
Budget year:
2018
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 9da1e0a576e7… | Mar 23, 2018 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NUEVA ECIJA 2ND DE | ₱48,885,768.86 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CF0158 | Apr 14, 2026 | REPAIR / REHABILITATION OF CLASSROOMS AT VEGA NATIONAL HIGH SCHOOL, BONGABON, NUEVA ECIJA | On-Going | ₱12.7M |
| 25CF0151 | Jan 5, 2026 | CONSTRUCTION OF 1STY2CL, CALAANAN ES, BONGABON, NUEVA ECIJA. | Completed | ₱4.9M |
| 25CF0121 | May 29, 2025 | ASSET PRESERVATION PROGRAM - REHABILITATION / RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE - SECONDARY ROADS - NUEVA ECIJA-AURORA RD - K0167+020-K0167+070 | Completed | ₱96.0M |
| 25CF0089 | Mar 24, 2025 | NETWORK DEVELOPMENT PROGRAM - ROAD WIDENING - SECONDARY ROADS - NUEVA ECIJA - AURORA RD - K0138+121.40-K0138+144, K0138+460-K0139+945 | Completed | ₱33.7M |
| 25CF0061 | Feb 25, 2025 | FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE, CALAANAN RIVER, LABI SECTION, BONGABON, NUEVA ECIJA | Completed | ₱96.5M |
| 25CF0026 | Feb 20, 2025 | FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG DIGMALA RIVER, PESA SECTION (LEFT SIDE), BONGABON, NUEVA ECIJA | Completed | ₱70.9M |
| 25CF0034 | Feb 14, 2025 | SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BONGABON, NUEVA ECIJA | Completed | ₱9.7M |
| 25CF0036 | Feb 14, 2025 | SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BARANGAY PESA, BONGABON, NUEVA ECIJA | Completed | ₱9.7M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.