Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 18CH0163

DPWH infrastructure contract
Contract ID:
18CH0163
Fingerprint:
4a97c6922b5fde…a523df535e Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jan 14, 2019 (7 yrs 9 mo ago) · Target/actual end Apr 13, 2019
Description:
REHABILITATION/RECONSTRUCTION/UPGRADING OF ROAD BARANGAY BATANG 1ST, SASMUAN, PAMPANGA
Category:
Roads
Implementing office:
DPWH Pampanga 2nd DEO · Region III
Contractor:
D.T. TIZON CONSTRUCTION AND TRADING · DPWH contractor code 38486
Contract amount:
₱2,001,925.85 (₱2.0M)
Funding source:
Outside Infra - GAA 2018 NDRRMF
Budget year:
2018

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
016958214ffe…Dec 19, 2018DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - PAMPANGA 2ND DEO₱2,000,200.18

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CH0082Sep 17, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING INCLUDING SITE DEVELOPMENT, BARANGAY CANGATBA, PORAC, PAMPANGAOn-Going₱99.0M
25CH0073Aug 18, 2025CONSTRUCTION OF PEDESTRIAN OVERPASS, MANCATIAN, PORAC, PAMPANGAOn-Going₱19.6M
25CH0074Aug 15, 2025CONSTRUCTION OF ROAD WITH DRAINAGE SYSTEM AT THE NEW PORAC MUNICIPAL HALL, BARANGAY CANGATBA PORAC, PAMPANGAOn-Going₱99.0M
25CH0059Aug 11, 2025REHABILITATION OF ROAD, SCTEX PORAC INTERCHANGE, PORAC, PAMPANGACompleted₱9.8M
25CI0066Aug 8, 2025SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG); SIPAG-FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATIGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF SLOPE PROTECTION AT LEONCIA BRGY STO DOMINGO, ANGELES CITYOn-Going₱29.4M
25CG0118May 27, 2025SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF EAST LATERAL MEGADIKE ROAD, MALIWALU, BACOLOR, PAMPANGACompleted₱58.4M
25CH0051Apr 21, 2025IMPROVEMENT OF ROAD, PHASE 2, BARANGAY HACIENDA DOLORES, PORAC, PAMPANGACompleted₱4.9M
25CH0054Apr 21, 2025CONSTRUCTION OF ROAD, PHASE 2, BARANGAY SINURA, PORAC, PAMPANGACompleted₱4.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.