Completed
Physical progress:
100%
Timeline:
Start Apr 19, 2018 (8 yrs 6 mo ago) · Target/actual end Oct 25, 2018
Description:
NETWORK DEVELOPMENT PROGRAM ROAD WIDENING PANIQUI-RAMOS RD - K0146+(-236) - K0146+000 (L/S), K0148+996.70 - K0149+160.00 (L/S), K0149+406.50 - K0149+640.00 (L/S), K0150+632 - K0151+546 (L/S), K0146+(-236) - K0148+345.80 (R/S), K0148+994.90 - K0149+348.7
Category:
Roads
Implementing office:
DPWH Tarlac DEO · Region III
Contractor:
R.R. RICAFORT CONSTRUCTION AND SUPPLIES · DPWH contractor code 14402
Contract amount:
₱61,533,211.68 (₱61.5M)
Funding source:
Regular Infra - GAA 2018 OO-1
Budget year:
2018

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
6e15fa38b51e…Mar 28, 2018DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - TARLAC DEO₱61,533,211.68

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CJ0141May 22, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (AUDITORIUM), BARANGAY POBLACION CENTER, RAMOS, TARLACCompleted₱18.8M
25CJ0216May 16, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG INERANGAN RIVER (ANNEX 6), RAMOS, TARLACCompleted₱96.5M
25CJ0196Apr 8, 2025REHABILITATION OF RAMOS ROAD NETWORK (ANNEX 2), RAMOS, TARLACCompleted₱99.0M
25CJ0207Apr 8, 2025CONSTRUCTION OF BARANGAY ROAD IN BARANGAY POBLACION SOUTH, RAMOS, TARLACCompleted₱9.6M
25CJ0208Apr 8, 2025CONSTRUCTION OF BARANGAY ROAD IN BARANGAY CORAL, RAMOS, TARLACCompleted₱9.9M
25CJ0140Mar 14, 2025ROAD WIDENING PANIQUI-RAMOS RD - K0150 + 621 - K0151 + 604On-Going₱18.4M
25CJ0155Feb 24, 2025CONSTRUCTION OF SUSUBAEN BY-PASS ROAD INCLUDING SLOPE PROTECTION STRUCTURE (PHASE 1), TARLACOn-Going₱99.0M
25CJ0156Feb 24, 2025CONSTRUCTION OF SUSUBAEN BY-PASS ROAD INCLUDING SLOPE PROTECTION STRUCTURE (PHASE 2), TARLACOn-Going₱99.0M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.