Completed
Physical progress:
100%
Timeline:
Start May 21, 2018 (8 yrs 5 mo ago) · Target/actual end Aug 6, 2018
Description:
CONCRETING OF PUROK 5, BRGY. PANCE FMR, BRGY. PANCE, RAMOS, TARLAC
Category:
Roads
Implementing office:
DPWH Tarlac DEO · Region III
Contractor:
R.R. RICAFORT CONSTRUCTION AND SUPPLIES · DPWH contractor code 14402
Contract amount:
₱5,678,793.60 (₱5.7M)
Funding source:
Outside Infra - GAA 2018 DA FMR
Budget year:
2018
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 5c92b702241f… | Apr 30, 2018 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - TARLAC DEO | ₱4,678,793.60 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CJ0244 | Jun 20, 2025 | CONSTRUCTION OF ACCESS ROAD LEADING TO ANAO TPLEX (SEGMENT 3), TARLAC | On-Going | ₱96.5M |
| 25CJ0269 | Jun 20, 2025 | CONSTRUCTION OF ACCESS ROAD LEADING TO ANAO TPLEX (SEGMENT 4), TARLAC | On-Going | ₱96.5M |
| 25CJ0188 | May 16, 2025 | CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG CADAANAN CREEK (ANNEX 7), ANAO, TARLAC | Completed | ₱96.5M |
| 25CJ0209 | Apr 8, 2025 | REHABILITATION OF ANAO ROAD NETWORK (ANNEX 2), ANAO, TARLAC | Completed | ₱96.5M |
| 25CJ0271 | Apr 8, 2025 | CONSTRUCTION OF ACCESS ROAD GOING TO ANAO TPLEX (SEGMENT 8), TARLAC | On-Going | ₱93.3M |
| 25CJ0272 | Apr 8, 2025 | CONSTRUCTION OF ACCESS ROAD LEADING TO TPLEX (PHASE 5), ANAO, TARLAC | On-Going | ₱144.8M |
| 25CJ0103 | Feb 17, 2025 | CONSTRUCTION OF ACCESS ROAD GOING TO ANAO TPLEX, PHASE F, ANAO, TARLAC | On-Going | ₱56.9M |
| 25CJ0023 | Jan 27, 2025 | CONSTRUCTION OF BY-PASS AND DIVERSION ROADS ANAO TO RAMOS ROAD, TARLAC | Completed | ₱50.0M |