Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 18CJ0174

DPWH infrastructure contract
Contract ID:
18CJ0174
Fingerprint:
78034784d53e6a…a334c671b9 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Aug 20, 2018 (8 yrs 2 mo ago) · Target/actual end May 6, 2019
Description:
ASSET PRESERVATION PROGRAM REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS ANAO-RAMOS RD - K0159 + (-504.40) - K0160 + 624.60, K0162 + 303 - K0163 + 206.50, K0163 + 206.50 - K0163 + 374 , K0164 + 942 - K0166+800
Category:
Roads
Implementing office:
DPWH Tarlac DEO · Region III
Contractor:
Contract amount:
₱92,157,422.44 (₱92.2M)
Funding source:
Regular Infra - GAA 2018 OO-1
Budget year:
2018

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
1d0dea1316fc…Jul 31, 2018DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - TARLAC DEO₱92,157,422.44

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CJ0244Jun 20, 2025CONSTRUCTION OF ACCESS ROAD LEADING TO ANAO TPLEX (SEGMENT 3), TARLACOn-Going₱96.5M
25CJ0269Jun 20, 2025CONSTRUCTION OF ACCESS ROAD LEADING TO ANAO TPLEX (SEGMENT 4), TARLACOn-Going₱96.5M
25CJ0188May 16, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG CADAANAN CREEK (ANNEX 7), ANAO, TARLACCompleted₱96.5M
25CJ0209Apr 8, 2025REHABILITATION OF ANAO ROAD NETWORK (ANNEX 2), ANAO, TARLACCompleted₱96.5M
25CJ0271Apr 8, 2025CONSTRUCTION OF ACCESS ROAD GOING TO ANAO TPLEX (SEGMENT 8), TARLACOn-Going₱93.3M
25CJ0272Apr 8, 2025CONSTRUCTION OF ACCESS ROAD LEADING TO TPLEX (PHASE 5), ANAO, TARLACOn-Going₱144.8M
25CJ0103Feb 17, 2025CONSTRUCTION OF ACCESS ROAD GOING TO ANAO TPLEX, PHASE F, ANAO, TARLACOn-Going₱56.9M
25CJ0023Jan 27, 2025CONSTRUCTION OF BY-PASS AND DIVERSION ROADS ANAO TO RAMOS ROAD, TARLACCompleted₱50.0M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.