FY2026 GAA: ₱6.79T
PisoScan

Project 18CJ0230

DPWH infrastructure contract
Hashed input (canonical JSON of the source row)
["dpwh","18CJ0230","CONSTRUCTION OF 4 STOREY 12 CLASSROOM, CARDONA NATIONAL HIGH SCHOOL, GERONA, TARLAC","Buildings and Facilities","Completed",34815380.02,0,100,"Tarlac DEO","Region III","R.R. RICAFORT CONSTRUCTION AND SUPPLIES (14402)","2018-12-04","2019-06-16",2018,"Outside Infra - GAA 2018 DepEd BEFF",15.57327,120.5884,"306906000","306900000"]
SHA-256
c6f678f0eb182d676080e70e988bc224f9c4ed5bd3c035c924987f4d091eb602