Project 18CK0109
DPWH infrastructure contract
Contract ID:
18CK0109
Fingerprint:
ed68c560191d95…77f4607382 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 28, 2018 (8 yrs 5 mo ago) · Target/actual end Sep 2, 2018
Description:
CONCRETING OF BARANGAY SAN ISIDRO (ALMENDRAS) - BARANGAY TALIMUNDOK MARIMLA FMR, BARANGAY SAN ISIDRO AND TALIMUNDOK MARIMLA, CONCEPCION, TARLAC
Category:
Roads
Implementing office:
DPWH Tarlac 2nd DEO · Region III
Contractor:
RAIK CONSTRUCTION AND DEVELOPMENT CORPORATION (FORMERLY: RAIK CONSTRUCTION AND SUPPLY) · DPWH contractor code 40660
Contract amount:
₱6,145,929.52 (₱6.1M)
Funding source:
Outside Infra - GAA 2018 DA FMR
Budget year:
2018
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CK0137 | Aug 20, 2025 | EMERGENCY REHABILITATION/RECONSTRUCTION OF EXISTING DIKE ALONG LUCUNG RIVER (MALUPA SECTION) DS OF LUCUNG BRIDGE, LEFT BANK, BRGY. MALUPA, CONCEPCION, TARLAC - PACKAGE C | Completed | ₱42.9M |
| 25CK0126 | Jun 13, 2025 | CONSTRUCTION OF SCHOOL BUILDING, MAGAO HIGH SCHOOL, BARANGAY MAGAO, CONCEPCION, TARLAC | Completed | ₱19.9M |
| 25CK0125 | May 20, 2025 | CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS - RAIN WATER COLLECTORS IN PUBLIC FACILITIES WITHIN 3RD LEGISLATIVE DISTRICT OF TARLAC, CONCEPCION, TARLAC | Completed | ₱2.6M |
| 25CK0075 | Apr 3, 2025 | REHABILITATION OF ROAD, LILIBANGAN - CASTILLO ROAD, CONCEPCION, TARLAC | Completed | ₱49.0M |
| 25CK0076 | Apr 3, 2025 | REHABILITATION OF ROAD AT BARANGAY LILIBANGAN TO CASTILLO ROAD, CONCEPCION, TARLAC | Completed | ₱96.5M |
| 25CK0083 | Apr 3, 2025 | REHABILITATION OF ROAD AT BARANGAY CASTILLO, CONCEPCION, TARLAC | Completed | ₱49.0M |
| 25CK0084 | Apr 3, 2025 | REHABILITATION OF ROAD AT BARANGAY SAN VICENTE, CONCEPCION, TARLAC | On-Going | ₱49.0M |
| 25CK0085 | Apr 3, 2025 | ASSET PRESERVATION PROGRAM: PREVENTIVE MAINTENANCE - TERTIARY ROADS ALONG CONCEPCION - LA PAZ ROAD, K0124+000.00 TO K0126+000.00, CONCEPCION, TARLAC | Completed | ₱96.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.